Project A has an internal rate of return (IRR) of 21 percent. Project B has an

  • 0 replies
  • 222 views
*

Offline mechanic

  • *****
  • 2565
    • View Profile
    • Engineering Forum
Question: Project A has an internal rate of return (IRR) of 21 percent. Project B has an IRR of 7 percent. Project C has an IRR of 31 percent. Project D has an IRR of 25 percent. Which of these would be the BEST project?

Options are:

a. Project A
b. Project B
c. Project C
d. Project D

Correct answer is:

c. Project C