What characteristic best describes the cost baseline?
« on: April 21, 2018, 08:02:13 PM »
Question: What characteristic best describes the cost baseline?

Options are:

a. Total budget for the project
b. Time phased budget for the project
c. Total budget for the project including the contingency budget
d. Total budget for the project including the contingency budget and the management
reserve.

Correct answer is:

b. Time phased budget for the project