Author Topic: 36 men can complete a piece of work in 18 days. In how many days will 27 men  (Read 638 times)

Offline mechanic

Advertisement
Question: 36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?

Options are:

A.     12
B.     18
C.     22
D.     24
E.     None of these

Correct answer is:

D.     24

Engineering Forum