Author Topic: An industrial loom weaves 0.128 metres of cloth every second. Approximately, how  (Read 600 times)

Offline mechanic

Advertisement
Question: An industrial loom weaves 0.128 metres of cloth every second. Approximately, how many seconds will it take for the loom to weave 25 metres of cloth?

Options are:

A.     178
B.     195
C.     204
D.     488

Correct answer is:

B.     195