Question: What characteristic best describes the cost baseline?
Options are:
a. Total budget for the projectb. Time phased budget for the project
c. Total budget for the project including the contingency budget
d. Total budget for the project including the contingency budget and the management reserve.

Correct answer:

b. Time phased budget for the project