1
Yes, DUT.

Have you got any email from DUT in previous month?
3
Scholarships / CSC Scholarship Study Plan
« Last post by fahad on Today at 10:06:04 AM »
Hello Friends,

If you are looking for help about writing an study plan for Chinese Government Scholarship (CSC) you are welcome to contact me with your query, I will be available to help your on this forum.

you just leave your question in a reply and i will help you answer that question.
4
"In process". DUT
l have also received mail from DUT but they did not ask me for medical report since l have submitted it during the application. they only said my application has been reviewed for scholarship  and l should not be worried about it but l can contact them if l have any question.

Thats very good, it means you have chance of admission in Dalian University of Technology.
5
"In process". DUT
l have also received mail from DUT but they did not ask me for medical report since l have submitted it during the application. they only said my application has been reviewed for scholarship  and l should not be worried about it but l can contact them if l have any question.
6
Electrical Engineering / Present worth is:
« Last post by mechanic on April 21, 2018, 08:03:59 PM »
Question: Present worth is:

Options are:

a. The discounted future cash flows to the present
b. The compounding present cash flows to the future
c. The current market value of the investment
d. The opportunity cost at the present value.

Correct answer is:

a. The discounted future cash flows to the present
7
Electrical Engineering / What characteristic best describes the cost baseline?
« Last post by mechanic on April 21, 2018, 08:02:13 PM »
Question: What characteristic best describes the cost baseline?

Options are:

a. Total budget for the project
b. Time phased budget for the project
c. Total budget for the project including the contingency budget
d. Total budget for the project including the contingency budget and the management
reserve.

Correct answer is:

b. Time phased budget for the project
8
Question: Project A has an internal rate of return (IRR) of 21 percent. Project B has an IRR of 7 percent. Project C has an IRR of 31 percent. Project D has an IRR of 25 percent. Which of these would be the BEST project?

Options are:

a. Project A
b. Project B
c. Project C
d. Project D

Correct answer is:

c. Project C
9
Question: Which of these is correct with respect to a product developed or a service performed?

Options are:

a. Bad quality is acceptable, but bad grade is not.
b. Bad grade is acceptable, but bad quality is not.
c. Neither bad grade nor quality is acceptable.
d. Grade and quality is the same thing.

Correct answer is:

b. Bad grade is acceptable, but bad quality is not.
10
Electrical Engineering / Quality control is aimed at:
« Last post by mechanic on April 21, 2018, 07:56:38 PM »
Question:Quality control is aimed at:

Options are:

a. Maintaining the desired quality
b. Exceeding the desired quality
c. Continuously improving the quality
d. Following the quality

Correct answer is:

a. Maintaining the desired quality
Pages: [1] 2 3 ... 10